Cabinet approves doubling of Barabanki-Akbarpur railway line

The Cabinet Committee on Economic
Affairs, chaired by the Prime Minister Shri Narendra Modi, has given its
approval for doubling of
Barabanki-Akbarpur railway
line
at an estimated cost of Rs.116.09 crore
and expected completion cost of Rs.1310.23 crore. 

 

The 161 km long railway line is
expected to be completed by 2021-22. 

 

Doubling of the line will greatly
ease the ever increasing passenger and freight traffic on
Barabanki-Akbarpur route
thereby increasing the revenue of Railways.  Besides travelling people,
industries in and around
Barabanki-Akbarpur route
will have additional transport capacity to meet their requirements.  The
districts of
Barabanki and Faizabad in Uttar Pradesh will
be benefited by this project.

 

Background:

            The
Barabanki-Akbarpur section falls in Lucknow Division of Northern
Railways.  At present detention of trains in Barabanki to Varanasi is high and
express trains are taking up to 7-15 hours in covering a distance of 323 km. 
Present capacity utilization from Barabanki to Faizabad is 146.5% and from
Faizabad to Akbarpur it is 152.6%.  This doubling will speed up the operation
and also provide additional capacity for meeting the requirement of increase in
traffic in future.

*****

AKT/VBA/SH